Case: Need for Large EV Fleet In The City of Seattle Public Utilities With Limited Electrical Capacity.

Scenario

The City of Seattle Public Utilities planned to add more than 40 electric vehicles to its fleet and needed for EV charging stations in Seattle. Because Clipper Creek’s made in USA EV charging stations were one of the very few charging station models approved by the City of Seattle at that time, the decision was made to install 40 of Clipper Creek’s HCS 40 (32 A charging stations) to charge Public Utilities fleet, consisting of sedans, mainly of Chevrolets. However, the main problem was the lack of power in the electrical panel. They had 400A available in the panel, which was not enough to have the whole EV fleet charged with independent dedicated circuits per charger.

Solution

Cyber Switching consulted to install an EV Management Controller (EVMC) layout to charge 40 electric vehicles and leverage the existing electrical service. This design drastically lowered the costs for an EV charger installation in Seattle as well as electrical conduit and wiring costs within the parking lots. The EVMC is capable of maximizing the use of the existing electrical infrastructure by feeding up to 4 EV charging stations using a single 40A branch circuit.

Results

After implementing this solution, every driver of the fleet now has a dedicated charger installed directly in their parking space and is able to get the electric cars fully charged overnight and ready for work by the morning when they come to work. Thanks to Cyber Switching, the City of Seattle Public Utilities now powers more than 100 fleet charging stations with more than 25 EVMC units, installed by a local certified electrical contractor.

Where the project stands today

About ten years in, the EVMC approach is still how Seattle Public Utilities grows its fleet charging. The City now runs more than 100 charging stations powered by more than 25 EVMC units.